BOI Approval Timeline: How Long Each Step Takes — and What Comes After (2026)
Published · Khonsu Legal
A BOI promotion in Thailand takes roughly 4–6 months from a well-prepared application to the promotion certificate, and realistically 6–12 months end-to-end once document preparation and correction rounds are counted. The official review window depends on your investment size — 40, 60 or 90 working days — and approval is not the finish line: it starts a compliance calendar of acceptance, capitalisation, incorporation and reporting deadlines, including the quarterly progress reports introduced in 2026, where two missed periods can cost you the promotion entirely.
This guide runs the clock through the whole journey. For what goes into the application — eligible activities, incentives, and how to prepare the project plan — see our companion guide to the BOI promotion application; this article is about how long each step takes and what you owe the BOI after the certificate arrives.
How long does each application stage take?
| Stage | Official / typical duration | What happens |
|---|---|---|
| Document preparation | 2–4 weeks (your side) | Project plan, financials, shareholding structure — quality here determines everything downstream |
| Submission and case assignment | 10 working days — the applicant's deadline, not BOI's | Application filed via e-Investment; you must contact the assigned case officer within 10 working days of submission to arrange the project presentation — missing this window can suspend the application |
| Officer interview / project presentation | As arranged with the case officer | You (or your representative) present the project and answer questions |
| Substantive review and decision | 40 / 60 / 90 working days by project size (see below) | Committee or sub-committee considers the project |
| Approval notification | Within ~7 working days of the decision | Formal approval letter with the conditions attached |
| Your acceptance of the approval | Within 1 month (30 days) of the approval notification, via e-Investment | Miss it and the approval lapses |
| Promotion certificate application | Within 6 months of acceptance | Requires the promoted company to exist (see below) |
| Certificate issuance | ~10 working days | The promotion formally begins |
Two honest caveats the official windows hide. First, the review clock runs on a complete application — every document round the officer requests pauses your real-world calendar even if not the official one. Second, the durations above are BOI service standards, not guarantees; complex projects, restricted activities and foreign-ownership questions add time.
Does project size change the timeline?
Yes — the substantive review window is tiered by investment value (excluding land and working capital):
| Investment size | Review window | Decided by |
|---|---|---|
| Up to ฿200 million | 40 working days | BOI office / sub-committee level |
| ฿200 million – ฿2 billion | 60 working days | Sub-committee / board level |
| Over ฿2 billion | 90 working days | Full board |
Working days, not calendar days: a 60-working-day review is roughly three calendar months, before adding the stages either side of it.
What must you do in the first six months after approval?
Approval starts a sequence of deadlines, each with a consequence:
| Obligation | Deadline | Where | If missed |
|---|---|---|---|
| Accept the approval and its conditions | Within 1 month (30 days) of the approval notification | e-Investment | Approval lapses (extensions possible on request) |
| Incorporate the promoted Thai company | In time to apply for the certificate (i.e. within the 6-month window) | DBD | Cannot apply for the certificate — see our company registration service |
| Bring in / pay up the registered capital | Per the approval conditions (first tranche typically within ~4 months of the approval) | Bank + DBD | Certificate delayed; conditions breach |
| Apply for the promotion certificate | Within 6 months of acceptance (extendable up to 3 times, 4 months each) | e-Investment | Approval lapses |
A practical sequencing note: if the promoted company does not exist yet, start incorporation immediately after acceptance — bank account opening, capital remittance and DBD registration comfortably consume the window if left late.
What are the ongoing reporting obligations — and what changed in 2026?
This is the part most guides skip, and the part that gets promotions suspended.
- Quarterly progress reports (new in 2026). Under Office Notification Por. 8/2569, promoted companies that have not yet reached full operation report project progress every quarter, within 30 days of the quarter-end, through the BOI's e-Monitoring system, from certificate issuance until the operating licence is granted. The deadline was 60 days when quarterly reporting was introduced in April 2026, and most published guides still print that figure; 30 days has been the rule since 20 May 2026. Non-filing can suspend the use of incentives, and missing two consecutive periods exposes the promotion to revocation. If your compliance calendar was built before April 2026 around the old twice-yearly reporting cycle, it is out of date.
- Annual operations report. Every promoted company files an annual performance report (traditionally due by 31 July) through the BOI's reporting system.
- Project audit. The BOI reviews whether the project was implemented as promised — machinery installed, capacity reached, conditions met — around the completion of the implementation period, before confirming full operation.
- Visa and work permit compliance. Foreign experts and executives brought in under BOI privileges are managed through the BOI's Single Window for Visa and Work Permit, the system that replaced e-Expert, with positions and headcounts that must match what was approved. The people privileges become usable once the promotion is in place — positions are approved in Single Window first, and the visas and work permits are then processed through the Thailand Investment and Expat Services Center (TIESC), typically in days rather than the weeks a standard work permit takes.
- Changing the project later. Capacity, location, scope, capital and shareholding are all conditions of the promotion — changing any of them requires a project amendment approved by the BOI before the change is made, not regularised after it.
- Condition-specific reports. Individual approval letters carry their own conditions — Thai shareholding levels, technology transfer, training plans — each of which is checkable and checked.
What deadlines apply to machinery and starting operations?
Two long-horizon deadlines shape the implementation phase:
- Machinery import: within 30 months of the certificate (for projects using the machinery import duty exemption), with the machinery list approved through the BOI's systems.
- Full operation / project implementation: within 36 months, meaning construction complete, machinery installed and the promoted activity actually operating.
Both are extendable on application with reasons — but extensions are requested before the deadline, not explained after it.
What happens if you miss a deadline — and can you extend?
The BOI's toolkit runs from mild to terminal: a warning or a request for clarification; suspension of the right to use incentives (duty exemptions stop working at customs); and withdrawal (revocation) of the promotion — which can include retroactive collection of the duties and taxes already exempted, because a revoked promotion is treated as if the privileges should not have been used.
The practical rules: diarise every deadline the day the certificate arrives; file the quarterly report even when nothing happened in the quarter (a "no progress" report filed on time is compliance; silence is not); and request extensions early with documented reasons — the BOI grants reasonable, well-founded extensions routinely, and almost never sympathises retroactively.
How long until the incentives actually work?
A question we hear from CFOs: the corporate income tax holiday runs from the date the promoted activity first earns revenue, not from the certificate date — so a slow implementation does not burn your tax holiday, but the machinery import window and implementation deadlines run from the certificate regardless. Plan the two clocks together: importing machinery in month 28 of 30 while revenue starts in month 20 wastes nothing, but the reverse sequencing can.
Two more mechanics worth planning around: for most incentive categories the total CIT exempted is capped by reference to the project's investment value (excluding land and working capital), and promoted revenue must be accounted for separately from any non-promoted business — the holiday only ever shelters the promoted activity.
This article is general guidance — not legal or tax advice. If you'd like a scoped opinion on how it applies to your specific situation, contact our team.
Frequently asked
How long does BOI approval take in total?
From filing to promotion certificate: roughly 4–6 months for a prepared application in the 40-working-day tier, and 6–12 months end-to-end including document preparation and post-approval steps. Larger projects (60/90-day tiers) run proportionally longer.
Can I speed the process up?
Not the committee stages — but the two biggest real-world delays are on the applicant's side: incomplete first submissions and slow responses to officer questions. A complete application with a well-prepared interview routinely beats a rushed one by months.
Do I need a Thai company before applying?
No — you can apply first and incorporate after approval (within the 6-month window). Many applicants do it in that order so the company is only formed once the incentives are certain.
What is the new quarterly reporting rule?
Promoted projects that have not reached full operation must file progress reports every quarter, each due within 30 days of the quarter-end, through the BOI's e-Monitoring system. The quarterly cycle replaced the old twice-yearly one in 2026, and the 30-day deadline is the one now in force under Office Notification Por. 8/2569 of 20 May 2026 — many published guides still print the 60 days set by the notification it replaced. Missing filings can suspend incentives, and two consecutive missed periods can lead to revocation.
What if the application is rejected — or approved with fewer incentives than expected?
Both happen. A partial approval can generally be discussed before you accept it — acceptance is your decision point, not a formality — and a rejected or withdrawn project can usually be restructured and refiled. Neither outcome blacklists the applicant; the cost is calendar time, which is another reason to get the first filing right.
Can I change the project after receiving the certificate?
Yes, but by amendment, not unilaterally: capacity, location, scope, capital structure and shareholding are promotion conditions, and each change needs BOI approval before it happens. An unapproved change discovered later is a conditions breach.
What happens if my promotion is revoked?
Beyond losing future incentives, the BOI can treat past privileges as improperly used — meaning retroactive collection of exempted import duties and taxes. Revocation is rare for companies that file on time and communicate; it is the endpoint of ignored deadlines, not honest delays.
Does the tax holiday start on the certificate date?
No — the CIT exemption period generally runs from the date the promoted project first generates revenue. The machinery and implementation deadlines, however, run from the certificate, so the two timelines must be planned together.
Can Khonsu manage the whole process?