The time required to obtain BOI promotion depends on the business activity, investment size, completeness of the application and complexity of the project. This article explains the principal stages of an application, the deadlines after approval, and the compliance obligations that follow.

Obtaining investment promotion from Thailand's Board of Investment (BOI) involves more than submitting an application and receiving approval. Investors must also complete several post-approval procedures and comply with ongoing conditions to maintain their investment privileges.

The time required to obtain BOI promotion depends on the proposed business activity, investment size, completeness of the application, and complexity of the project.

Under the BOI's standard procedures, project evaluation generally takes 40, 60 or 90 working days, depending on the investment value. However, these periods do not cover every stage of the process, including document preparation, project clarification, company registration and issuance of the investment promotion certificate.

This article explains the principal stages of a BOI application, the deadlines following approval and the compliance obligations that investors should understand before commencing their promoted activities.

### 1. How Long Does BOI Approval Take?

The BOI applies different project evaluation periods according to the proposed investment value, excluding the cost of land and working capital.

| | Investment Value | Official Evaluation Period |
| --- | --- | --- |
| Not exceeding THB 200 million | 40 working days |
| Exceeding THB 200 million but not exceeding THB 2 billion | 60 working days |
| Exceeding THB 2 billion | 90 working days |

These periods are calculated from the submission of complete application documents and are subject to the applicable BOI evaluation procedures.

They should not be treated as guaranteed completion dates.

The overall process may take longer where the BOI requires additional information, clarification of the proposed business model, amendments to the application or supporting documentation.

Investors should therefore distinguish between the BOI's official project evaluation period and the total time required to obtain a promotion certificate.

### 2. What Are the Main Stages of the BOI Application Process?

#### Step 1: Application Preparation and Submission

The process begins with identifying the appropriate BOI-promoted activity and confirming that the proposed project satisfies the applicable eligibility criteria.

The applicant must prepare information describing the business, proposed investment, operations and other matters relevant to the particular activity.

For most general investment promotion applications, submission takes place through the BOI's e-Investment system.

An accurate and sufficiently detailed application is important because the BOI evaluates the proposed project against the relevant promotion criteria. Incomplete information or inconsistencies may lead to additional questions and delays.

#### Step 2: Project Clarification

After submission, the applicant is required to clarify the proposed project with the responsible BOI officer.

This may involve a meeting or presentation addressing the proposed activities, investment plan, business operations and compliance with the relevant promotion requirements.

Depending on the nature of the project, the officer may request additional information or documents before proceeding with the evaluation.

Applicants should be prepared to explain how the proposed business will operate in practice, rather than relying solely on a general business description.

#### Step 3: BOI Evaluation and Decision

Once the application is sufficiently complete, the project proceeds through the applicable evaluation and approval process.

The relevant authority considers the project according to its investment size and the applicable BOI criteria.

The BOI's standard evaluation periods are 40, 60 or 90 working days, as outlined above.

Following the relevant decision, the applicant is formally notified of the result and, where approved, the conditions attached to the investment promotion.

An approval may include specific requirements relating to the approved activities, investment, business location, operational arrangements, or other matters relevant to the project.

Applicants should carefully review these conditions before accepting the promotion.

### 3. What Happens After BOI Approval?

BOI approval and issuance of the investment promotion certificate are separate stages.

Receiving an approval notification does not mean that all post-approval formalities have been completed.

The applicant must accept the approval and apply for the promotion certificate within the prescribed periods.

#### Acceptance of the BOI Approval

The applicant generally has one month from receipt of the approval notification to formally accept the BOI's resolution.

Acceptance is completed through the applicable BOI promotion certificate procedure.

The applicant should review the approved business activities, investment requirements and other conditions before confirming acceptance.

Where additional time is necessary, an extension may be requested under the applicable BOI procedures. Such extensions should not be assumed to be automatic.

#### Application for the Promotion Certificate

Following acceptance, the applicant generally has six months to submit the application and supporting documents for issuance of the investment promotion certificate.

For a newly established Thai company, incorporation must be completed before the certificate can be issued.

Depending on the circumstances, the supporting documents may include corporate registration documents, shareholder information, evidence of foreign investment funds, and other information required by the BOI.

Once the application and supporting documents are complete, the BOI's standard period for issuing the promotion certificate is 10 working days.

The applicant should also check the conditions relating to registered capital, paid-up capital and evidence of investment applicable to the particular project.

### 4. What Are the Main Obligations After Receiving the Promotion Certificate?

The promotion certificate sets out the approved activities, investment privileges and conditions governing the promoted project.

Compliance does not end when the certificate is issued.

The company must implement the project in accordance with the approval and maintain appropriate records demonstrating compliance with the applicable conditions.

The principal obligations generally include project implementation, progress reporting, compliance with investment requirements and proper utilisation of BOI privileges.

#### Project Implementation and Commencement of Operations

Under the general BOI framework, promoted projects are normally required to complete the necessary investment and apply for approval of full commencement of operations within the prescribed implementation period.

For many projects, the standard period is 36 months from the issuance of the promotion certificate, although different conditions or exceptions may apply.

For BOI purposes, approval of full commencement of operations is not necessarily the same as the date on which a company first begins selling products or providing services.

The approval process involves verification that the promoted project has been implemented in accordance with the relevant investment and operational conditions.

Investors should therefore check both the implementation deadlines and the specific requirements for obtaining the BOI's formal approval of full operations.

#### Machinery Importation

Where the promoted project receives import duty privileges for qualifying machinery, the company must comply with the relevant machinery approval and importation requirements.

For many projects, the standard machinery importation period is 30 months from the issuance of the promotion certificate.

However, this period does not apply uniformly to every activity or category of machinery.

Companies should verify the applicable importation period and approval procedures before importing machinery under BOI privileges.

#### Changes to the Approved Project

A promoted company may need to obtain BOI approval or make the required notification before implementing certain changes to its approved project.

Depending on the applicable conditions, these may include changes to:

- The nature or scope of the promoted activities.

- Investment or production capacity.

- Business location.

- Shareholding or corporate structure.

- Other material conditions stated in the promotion certificate.

Not every corporate or operational change is subject to the same approval requirements.

The appropriate procedure must be determined by reference to the particular change and the conditions applicable to the project.

### 5. BOI Reporting Requirements: What Changed in 2026?

An important regulatory development in 2026 concerns the frequency of project progress reporting.

Under BOI Notification No. 8/2569, dated 30 March 2026, and [Office of the BOI Notification No. Por. 8/2569](https://www.boi.go.th/upload/content/por8_2569_6a0e6ed158b7b.pdf), dated 20 May 2026, promoted projects are required to submit quarterly progress reports through the BOI's e-Monitoring system.

#### Quarterly Progress Reporting

Promoted projects that have not yet received the BOI's approval for full commencement of operations must report their progress quarterly.

The relevant reporting periods end in March, June, September and December.

Each quarterly progress report must be submitted within 30 days after the end of the relevant quarter.

The reporting obligation generally applies from issuance of the promotion certificate until the project receives approval for full commencement of operations.

For certificates issued during a quarter, the first report is due for the following applicable reporting period.

The 2026 requirements also apply to existing promoted projects, replacing the previous twice-yearly progress reporting conditions.

#### What Happens if a Company Does Not Report?

Failure to submit the required progress report may result in suspension of the company's ability to use BOI privileges.

Where the company fails to report for two consecutive periods, the BOI may consider revoking the relevant rights and benefits.

Revocation is not necessarily automatic, but the consequences can be significant.

Promoted companies should therefore maintain a reporting calendar and ensure that the relevant submissions are completed on time, including where project implementation has been delayed.

#### Annual Performance Reporting

In addition to quarterly progress reports, promoted companies are subject to applicable annual performance reporting requirements.

Companies that have received approval for full commencement of operations are generally no longer required to submit quarterly project progress reports, but must continue submitting the required annual performance information.

The annual reporting process is generally administered through the BOI's e-Monitoring system during the prescribed reporting period.

Additional reports may be required where the promotion certificate contains activity-specific or special conditions.

### 6. When Can a Company Start Using BOI Incentives?

The timing and conditions for using BOI incentives depend on the type of privilege granted.

Investors should not assume that every incentive becomes available automatically upon receiving the approval notification.

For example, machinery import duty privileges require compliance with the applicable approval and importation procedures.

Where a project receives a corporate income tax exemption under the Investment Promotion Act, the exemption period is generally calculated from the date the promoted activity first generates qualifying income, rather than simply from the date the promotion certificate is issued.

However, the company must satisfy the relevant conditions before claiming the exemption.

The formal BOI approval for full commencement of operations may occur after the company has begun generating income from its promoted activities.

These events should therefore be distinguished when planning the project's implementation and tax compliance.

Companies carrying out both promoted and non-promoted activities must also maintain appropriate accounting records to identify the income and expenses attributable to the promoted business.

### 7. What Happens if a Company Cannot Meet a BOI Deadline?

The consequences of missing a BOI deadline depend on the obligation concerned and the conditions attached to the project.

Certain procedural and implementation deadlines may be extended where the applicable BOI rules permit and sufficient grounds are demonstrated.

However, extensions are not automatic.

Where a company anticipates that it cannot meet a deadline, it should assess the applicable extension procedures and submit any necessary request before the deadline expires.

Failure to comply with material promotion conditions may result in restrictions on the use of incentives, withdrawal of rights and benefits, or revocation of investment promotion.

Depending on the circumstances, the company may also face tax or customs consequences in relation to incentives previously claimed.

Early assessment of potential compliance difficulties is therefore important.

### 8. Practical Considerations for Foreign Investors

Foreign investors planning a BOI application should consider the entire process, not only the expected approval period.

In particular, the following matters should be addressed at an early stage:

- Business eligibility: Confirm that the actual proposed activities satisfy the relevant BOI criteria.

- Corporate structure: Determine whether the Thai company will be incorporated before or after the initial application, and ensure that the final structure complies with the approved conditions.

- Capital and funding: Plan the required investment, capitalisation and supporting evidence.

- Project implementation: Establish a realistic operational schedule that reflects the applicable conditions.

- Ongoing compliance: Maintain records, reporting procedures and a calendar of BOI deadlines.

A well-prepared application may help reduce avoidable delays. Equally important, however, is the company's ability to implement and maintain the promoted project after approval.

### Conclusion

BOI investment promotion involves several distinct stages, from preparing and submitting an application to accepting the approval, obtaining the promotion certificate and complying with post-approval requirements.

Although the BOI generally applies project evaluation periods of 40, 60 or 90 working days, the total process depends on the circumstances of the proposed investment.

Once promotion is granted, the company must continue complying with the approved project conditions, implementation deadlines and reporting requirements, including the quarterly progress reporting framework introduced in 2026.

For foreign investors, effective BOI planning requires more than securing approval. It requires establishing a business that can operate within the approved scope and maintain its investment privileges over time.

This article provides general information on Thai investment promotion procedures as of November 2026 and does not constitute legal or tax advice. The applicable requirements and deadlines depend on the relevant BOI rules and the conditions of each promoted project.

This article is general guidance — not legal or tax advice. If you'd like a scoped opinion on how it applies to your specific situation, [contact our team](https://khonsulegal.com/contact/).

FAQ

### Frequently asked

#### How long does BOI approval take in total?
The BOI's project evaluation period is generally 40, 60 or 90 working days, depending on the investment value, counted from the submission of complete application documents. These periods are not guaranteed completion dates, and they do not cover every stage of the process, including document preparation, project clarification, company registration and issuance of the promotion certificate. The total time depends on the business activity, investment size, completeness of the application and complexity of the project.

#### Can I speed the process up?
A well-prepared application may help reduce avoidable delays. The BOI evaluates the project against the relevant promotion criteria, and incomplete information or inconsistencies may lead to additional questions and delays. Applicants should be prepared to explain how the proposed business will operate in practice, rather than relying solely on a general business description.

#### Do I need a Thai company before applying?
Not necessarily. Investors should decide whether the Thai company will be incorporated before or after the initial application. For a newly established Thai company, incorporation must be completed before the promotion certificate can be issued, and the certificate application must generally be made within six months of accepting the approval.

#### What is the new quarterly reporting rule?
Under BOI Notification No. 8/2569 and Office of the BOI Notification No. Por. 8/2569, promoted projects that have not yet received approval for full commencement of operations must submit quarterly progress reports through the BOI's e-Monitoring system, each within 30 days after the end of the relevant quarter. The requirement also applies to existing promoted projects, replacing the previous twice-yearly progress reporting conditions.

#### Can I change the project after receiving the certificate?
Certain changes require BOI approval or a notification before they are implemented, depending on the applicable conditions. These may include changes to the nature or scope of the promoted activities, investment or production capacity, business location, and shareholding or corporate structure. Not every corporate or operational change is subject to the same approval requirements.

#### What happens if my promotion is revoked?
Failure to comply with material promotion conditions may result in restrictions on the use of incentives, withdrawal of rights and benefits, or revocation of investment promotion. Depending on the circumstances, the company may also face tax or customs consequences in relation to incentives previously claimed.

#### Does the tax holiday start on the certificate date?
Generally not. Where a project receives a corporate income tax exemption under the Investment Promotion Act, the exemption period is generally calculated from the date the promoted activity first generates qualifying income, rather than simply from the date the promotion certificate is issued. The company must satisfy the relevant conditions before claiming the exemption.

Related insights

25 August 2026

#### How to get BOI promotion in Thailand: a 2026 application guide

An overview of BOI promotion in 2026: what it grants, how eligibility is assessed, the stages of an application, and the conditions that continue after promotion.

See: https://khonsulegal.com/insights/boi-promotion-application-2026/

31 May 2026

#### BOI Promotion for Technology Businesses in Thailand: Which activity categories suit your tech businesses?

Which BOI activity categories fit technology businesses in Thailand — software development and modification, digital infrastructure, digital ecosystem and smart-city projects, and the practical distinctions to consider before applying.

See: https://khonsulegal.com/insights/boi-activities-tech-2026/

31 May 2026

#### Setting up a Treaty of Amity company in 2026

Who qualifies for a US-Thai Treaty of Amity company in 2026, the two-step certification process, capital rules, realistic timelines — and when BOI promotion is the better route.

See: https://khonsulegal.com/insights/treaty-of-amity-2026/

### Ready to take the next step?

Schedule a consultation with our multilingual legal and accounting team.

---
Disclaimer: Khonsu Legal is a private law firm providing independent legal, corporate, tax and immigration services. We are not affiliated with any government agency or official department.